The concrete pour was completed earlier this week. The concrete contractor will be back on Monday (3/9) to address any issues, final clean up, and remove his equipment.
Next stage is the All Steel building construction, tentatively scheduled for Mar 16. Should be able to confirm the date on Monday (3/9).
The final stage is electrical work, which will be scheduled on it about Mar 18.
Pictures of the work in progress